Install/Commission

Instrument installation and commissioning performed by Bay-Tec provides our customers with a single point of responsibility for an entire system. A Foreman will work closely with our Project Manager to insure coordination issues are addressed in project meetings, and carried out in the field.

All Bay-Tec Instrument Technicians are highly trained, experienced, and have a strong knowledge of Bay-Tec's testing procedures and start-up practices. This continuity between engineering and construction allows for a streamlined start-up with proper testing and commissioning documentation generated to support upcoming validation efforts.

Bay-Tec's commissioning Turn-Over-Package includes:

DOCUMENTATION FUNCTION
Instrument Bench Checkout Test Forms
  • Instruments are calibrated to NIST traceable standards upon receipt
    at Bay-Tec to insure functionality and accuracy prior to installation.
Documented Loop Checkout Forms
  • Loops are tested from field device, through the I/O and verified at control consoles.
Field GMP Calibration Record Forms
  • Instruments calibrated in the field, are calibrated using NIST traceable
    standards per cGMP SOP's.
Site Acceptance Test (SAT)
  • After hardware has been installed and loops checked, the entire
    system is functional tested for operation per design documents.